61 | Medium | 5/2/2022 | Implement Document Repository (FileNet) for LAB Final Records | Planning - 11/29/2022 | Project kickoff meeting took place on 11/28/2022 and the project planning is in process | TBD | Srividhya Ramamoorthy | Shabab Shams | None |
147 | High | 7/30/2021 | Upgrade FileNet | Closure - 12/05/2022 | Upgrade has been completed | 12/16/2022 | Dean Wyley | Dan Boulger | Extending completion date by two weeks so IT resources can be available for a two-week, post-upgrade warranty period. |
157 | Medium | 3/1/2022 | 2019 SharePoint Intranet Sites upgrade | Closure - 12/11/2022 | Upgrade has been completed | 12/29/2022 | Jeff Vail | Cassandra Kline | Extending completion date by two weeks so IT resources can be available for a two-week, post-upgrade warranty period. |
166 | High | 1/4/2021 | Upgrade SASD Maximo eco system | Execution - 11/01/2021 | TEST has been fully migrated to the physical SQL cluster. Validation of TEST on the new cluster is 70% and is on track to be completed by first week of January. Expecting UAT to be completed and signed off by Don Keene and UAT team by 12/16/2022. PROD environment is being built out ahead of schedule. Everything is tracking for our expected Go Live at the end of February. | 2/28/2023 | Luisa -Maria Gomez | Vu Pham | None |
191 | High | 8/2/2021 | Sunset IE Support | Planning -09/01/2022 | The first phase was rolled out on 10/12/2022 which defaulted to the Edge browser and pushed out the Edge configuration for the outstanding apps that still require Edge compatibility mode or IE redirect. The rollout did encounter unforeseeable issues due to personal settings and profiles of District staff. The help desk staff along with Tina Cady worked tirelessly to identify a root cause and rolled out a fix that appears to have limited further reported incidences. Now that the first phase is in a steady state, the project has been moved back to the execution phase to work on the outstanding links for remediation as they can be worked on by technical staff with timesheets being the first application to be addressed. Will be working with customers to identify the list of issues that have been identified when using timesheets on Edge. | 6/30/2023 | Dan Boulger | Kerri Stewart | The target date is changing due to the number of links that will need remediation in this project. The timesheet application was reviewed by technical staff and it was determined that the remediation for the single application, to work in Edge, would a be a large effort of 200+ hours. The goal has been redefined to fix specific issues instead reworking the entire application. However there are 30 more applications that need to go through this evaluation of identifying the specific issues and getting them resolved. There’s also limited technical staff to complete the remediation. |
170 | Medium | 3/16/2022 | Migration to Atlassian Cloud | Execution - 10/21/2022 | Test Migration #1 is underway with estimated completion date of 12/16/2022. Test Migration #2 is scheduled to begin on 12/19/2022 with an estimated completion date of 01/31/2023. Start of final migration is scheduled to begin 03/2023. Final migration date is TBD. | 4/28/2023 | Jeff Vail | Liz White | Extending completion date by 60 days to address unexpected problems discovered during Test migration # 1 and to include 30 days warranty period after the project has been completed |
195 | Medium | 5/20/2022 | Develop RFP for ERP system | Initiation - 05/20/2022 | Meeting between IT and Soft Resources (Consultant) was conducted on 12/12/2022. Meeting with GM/CEO is scheduled for 12/19/2022 for Soft Resources. The kick off meeting between the consultant and stakeholders has been scheduled for January 5, 2022 | 11/17/2023 | Matt Doyle | Arshad Waheed | None |
198 | High | 10/18/2022 | Implement LIMS Instrument Interface | Initiation - 11/29/2022 | Project Charter has been completed and is waiting for approval of Srivi so that the kick off meeting of stakeholders can be scheduled | TBD | Srividhya Ramamoorthy | Shabab Shams | None. |
199 | Medium | 11/22/2022 | Consolidated SacSewer/Regional San Web Content Management System (WCMS) | Initiation - 12/12/2022 | Project charter is being prepared for approval of the stakeholders | TBD | Nicole Coleman | Liz White | None |
200 | Medium | 12/13/2022 | Grant JIRA Access to CMMS to Support the Regional San Operations Business Systems Change Request Process | Ready to Initiate - 12/13/2022 | Preparing to initiate the project | TBD | Dean Wyley | Phillip Agee | None |
192 | Medium | 12/7/2022 | Regional San Interceptor Documentation Migration to SASD Project | Initiation -12/09/2022 | Project charter is being prepared for approval of the stakeholders | TBD | Amber Schalansky | Shabab Shams | None |
|
|
|
|
|
|
|
|
|
|
| | | | | | |
| | |
ITSD-6742 | High | 5/12/2022 | Revise the IT Projects list Report | Completed | Completed and closed | N/A | Luisa -Maria Gomez and Thea Durbin | Shabab Shams | Successfully implemented |
ITSD-12433 | High | 8/9/2022 | Servers and vendor accounts for flow monitoring data analysis software | Waiting to initiate | This is a customer managed project. IT shall assist the customer with purchase of required servers and with the commissioning plan as soon as the project manager Don La Franchi has obtained security approval from Catherine Wild | TBD | Don La Franchi | Phillip Agee | Customer Managed project. Don La Franchi of SASD is the Project Manager who has to obtain security approval from Catherine Wild before IT can help order the equipment and help him with commissioning of servers |
ITSD-11426 | High | 5/6/2022 | LIMS Lab Instrument Interface Conversion | Closed/converted to initiative-198 | Solution analysis was completed on 10/18/22. IT approval and ETSC approvals were obtained and the project has been initiated as initiative-198 as reported in the first section of this report | Closed/ completed | Srivi Ramamoorthy | Shabab Shams | Project has been initiated as initiative-198 |
ITSD-13828 | Medium | 8/24/2022 | Monday.com Project Management software Pilot project | Solution Analysis | The customer has decided to purchase the Monday.com software; Enterprise version and is waiting for the quotation from the vendor so that purchasing process can be initiated. | 12/23/2022 | Jennifer Weitz | Phillip Agee | The targeted completion of the ITSD has been delayed by 21 days because IT is waiting on customer to make purchasing related decision before next steps can be taken. |
ITSD-13726 | Medium | 10/6/2022 | Grant JIRA Access to CMMS to Support the Regional San Operations Business Systems Change Request Process | Closed/converted to initiative-200 | IT has completed the review and interactive demo of JIRA with the customer. The customer has approved to move forward on this project. High level requirements have been gathered by the asssigned PM | 12/13/2022 | Thea Durbin | Phillip Agee | Project has been initiated as initiative-200 |
ITSD-11589 | High | 5/12/2022 | Lab Final Records Repository in FileNet | Closed/converted to initiative-61 | Solution analysis was completed on 09/15/22. IT approval and ETSC approvals were obtained and the project has been initiated as initiative-61 as reported in the first section of this report | Closed/ completed | Srivi Ramamoorthy | Shabab Shams | Project has been initiated as initiative-61 |
ITSD-11431 | Medium | 8/16/2022 | Confluence Grant management system | Solution Analysis | IT Needs Assessment document approved by Mike and Christoph for the Confluence Program has been provided to IT on 11/09/2022 by Carolyn Balazs with the request that meeting be set up in mid-December to discuss the document. Meeting has been confirmed for 12/28/2022 | TBD | Carolyn Balazs | Shabab Shams | Solution analysis process was suspended until November 2022 per request from Carolyn Balazs who is the customer contact designated by Mike Huot. |
ITSD-14134 | High | 9/16/2022 | Assess off-the-shelf FileNet for reports W/O EDM/RDA | Solution Analysis | Functionality review with Fairfax has been completed and it has been determined that of the new version of FileNet 8.5 which has been implemented successfully on 12/05/2022 shall meet the requirements which are being currently addressed by EDM/RDA so EDM/RDA can be replaced with "out of box" user interface; ICN which shall require certain customization to be performed by FairFax. The project manager has requested FairFax to provide quotation and schedule. | 12/30/2022 | Thea Durbin | Shabab Shams | Waiting for FairFax to provide quotation for customization services and schedule of delivery so that it can be presented for approval |
ITSD-12235 | Medium | 5/12/2022 | Add batch functionality features to RDA application | Waiting to initiate | ETSC approval was granted on 10/28/2022. The project team and the customer (Dean Wyley and the documentation team) are in process of determining if this project will be needed after upgrade of FileNet to the newer version | TBD | Dean Wyley | Shabab Shams | None |
|
|
|
|
|
|
|
|
|
|
** Only those ITSDs are reported here which have been identified as a higher priority by the customer |